Projects

Factory and production-system projects.

Selected references from automotive, aerospace, supplier and industrial manufacturing environments.

5 Core industries
International Europe, India, USA
Plant engineering From layout to ramp-up
Automotive · India

Implementation-ready line

Final Assembly Planning for Powertrain Systems

Initial situation: Greenfield planning for medium to heavy-duty gearboxes.

CMF approach: Concept variants, station workshops, technical specifications and supplier process.

Result: Implementation-ready line concept with structured realization path.

Aerospace

Target concept adopted

Factory Structure Analysis and Target Design

Initial situation: Rising output rates with new product requirements.

CMF approach: Baseline analysis, feasibility, logistics and process design.

Result: Approved target concept with clear implementation sequence.

Automated hairpin stator assembly Automotive · Stator assembly

80 stakeholders · 3 months pulled forward

Stator assembly for electric vehicles

Initial situation: Ongoing plant project, taken over in procurement shortly before internal assembly. Relocation to be pulled forward by three months.

CMF approach: Project leadership and customer interface, budget-schedule-resource control, team setup, full relocation replanning within one month, coordination of up to 80 stakeholders, ramp-up support.

Result: On-time relocation over year-end against the new plan. Issue analysis and measures during line start-up.

Electric mobility and battery systems Automotive · Battery assembly

On-schedule acceptance DE/UK

Battery assembly line for electric vehicles

Initial situation: Technical project lead for a battery production line, sites in Germany and the UK. Direct OEM production-planning interface, change orders, capability studies and supply constraints.

CMF approach: Shopfloor and customer alignment, steering of rebuilds and open-point lists through to close-out, SAP maintenance, alignment across mechanics, electrics, software, quality, documentation and safety, weekly status reporting.

Result: On-schedule plant acceptance despite complex change.

References

Long-term client relationships.

These names illustrate experience across complex industrial programs along the full value chain.

Selected references

Airbus · Audi · Mercedes-Benz · Accumotive · Assembly Test Europe (ATW) · Corza Medical · Siemens · Felsomat · Detroit Diesel · GETRAG FORD · Grob-Werke · Vaillant · 3M · Qiagen · Heraeus · Fissler · AL-KO · Intersnack · Schöck · Hays · P3 Engineering